Is it possible to cascade synchronization checks?

Does this make sense at all?

Thanks
GWright
 
Posts: 1
Joined: Mon Apr 25, 2016 1:34 pm

Re: Cascade synchronization check question

Postby eValid » Tue Apr 26, 2016 7:22 am

GWright wrote:Afternoon:

Is it possible to cascade synchronization checks?

Does this make sense at all?

Thanks


Thanks for the question GWright.

Yes, setting up an AJAX page synchronization that involves double or even triple synchronization steps is possible and is recommended for some kinds of pages.

Here is a worked example that shows how this goes:

http://www.e-valid.com/Products/Documen ... .sync.html

Not that in this example successfully sync commands (shown in RED on the page) happen once after the other.

You may want to intersperse some "Delay 100" commands to make sure everything in the page has stabilized before applying the next synchronization check(s).

-- eValid Support
eValid
 
Posts: 2392
Joined: Tue Jan 01, 2008 12:48 pm
Location: USA


Return to Technology

Design Downloaded from free phpBB templates | free website templates | Free Web Buttons